Community information on current works

Road Construction

  • Marnie Road, Glen Forrest – Pending improvement in weather before carpark construction
  • Katharine Street, Helena Valley Noel St to Wilkins Rd – Asphalt resurfacing. 80% complete. Remaining portion of top layer asphalt Elder Way to Wilkins delayed due to subdivision works.
  • Swan View Road, Swan View Old York Road to Curve Road – Asphalt resurfacing. Bottom layer, drainage, kerbing and footpath works to be completed throughout July.
  • Ealy Street, Mount Helena Royston Place to Dibble Street – Works awarded, late July commencement.

Footpath Construction

  • Bladon Way, Swan View Concrete Footpath – Drainage, kerb and footpath works.

Parks and Ovals

  • Harmony Park, Parkerville - Playground installation.
  • Brown Park – New Power Cabinet.
  • Triandra Park Playground - New play equipment to be installed. 
  • Broz Park – Playground works.
  • Buninyong Road – Road Reserve Landscaping Works.

Buildings

  • Parkerville Oval Shelter - Structural repairs.

 

View current public notices for infrastructure projects, works and upgrades